This 776-acre, up to 1.25 GW proposal sits inside the 10,000-acre Entrata master plan near White Hills in northern Mohave County. Also known as: Entrada.
Power1,250MW reported · stated
Site776acres
Who is behind it
ProjectEntrata Data CenterAlso: Entrada
Developer and teamClean Cloud Energy
End userNot found in the recordsNot yet named in any record or credited report we have found.
The record, newest first
AZBEX reported a 776-acre, up to 1.25 GW plan on the Entrata master-plan land, with construction aimed at 2027-28. (AZBEX, Dec. 16, 2025)
At the meeting where Mohave County adopted its data center SUP rules, staff said Entrata had applied first and may be exempt. (Kingman Daily Miner, Dec. 2025; AZBEX, Dec. 16, 2025)
Conflicts and open questions
- The Kingman Daily Miner spells the project 'Entrada'; AZBEX spells it 'Entrata'.
- The master plan size is printed as '10,00-acre' in AZBEX (likely 10,000).
- Coordinates are approximate.
The full record
- Status note
- A preliminary site plan was submitted. AZBEX said the SUP exemption was undetermined; the Kingman Daily Miner reported the project exempt because it applied first.
- Power note
- Up to 1.25 GW stated by project representatives
- Evidence
- News reports; primary records not yet obtained
- Size class
- 50 MW or more (tracker scope)