Data center campus · Avondale (operator gives no address; likely the Hermosa Ranch site south of Avondale Blvd and Lower Buckeye Rd), Maricopa County, Arizona

Prime Data Centers Phoenix campus (PHX01)

Under construction as of May 21, 2026

Prime is building a five-building hyperscale campus on 66.5 acres in Avondale, with the first three buildings leased to an unnamed hyperscale customer and a dedicated on-site substation. Also known as: Prime PHX01.

Cite← Arizona data centers
Apache CountyCochise CountyCoconino CountyGila CountyGraham CountyGreenlee CountyLa Paz CountyMaricopa CountyMohave CountyNavajo CountyPima CountyPinal CountySanta Cruz CountyYavapai CountyYuma CountyPrime Data Centers Phoenix campus (PHX01) · Under construction · 240 MW
Power240MW reported · stated
Floor area1,300,000sq ft
Site66.5acres
IT load240MW

Who is behind it

ProjectPrime Data Centers Phoenix campus (PHX01)Also: Prime PHX01
Developer and teamPrime Data Centers
End userUnnamed hyperscaler has secured buildings 1-3

The record, newest first

  1. Prime announced groundbreaking on buildings 1-3 (48 MW each), said phase 1 of a roughly 250 MW on-site substation is commissioned, and raised the investment to $3 billion. (Business Wire (Prime Data Centers release), May 21, 2026; CommercialSearch, May 22, 2026)

  2. Prime announced a 210 MW, 66-acre, five-building Avondale campus, with the first building targeted for Q3 2025. (Data Center Frontier, May 4, 2023)

  3. AZBEX reported a revived PAD rezoning and general plan request for about 1.3M sq ft of data centers in five buildings at the Hermosa Ranch Technology Park site in Avondale, after an earlier request was withdrawn; the story does not name the developer. (AZBEX, Aug. 9, 2022)

Conflicts and open questions

  • The 2022 AZBEX story does not name Prime in its text (only in its tags); the link to Prime is inferred from matching scope (1.3M sq ft, five buildings) and city. Treat the place and the 2022 event as inferred.
  • Utility not named in sources; power via a dedicated on-site substation of about 250 MW.
  • Evidence is reported: the 2026 announcement is a company press release; no Avondale approval document for the Prime parcel was opened.
  • The 2023 'more than $2 billion' figure is from Avondale's mayor quoted by Data Center Frontier.

The full record

Status note
Groundbreaking on the first three of five buildings announced May 21, 2026.
Power note
240 MW of critical IT capacity at full build; first phase 144 MW (three 48 MW buildings). 2023 announcement said 210 MW.
Evidence
News reports; primary records not yet obtained
Size class
50 MW or more (tracker scope)
Map position approximate, from the reported address or area. Updated Oct. 17, 2026.