Project Eagle / Project Baccara
Takanock plans a 160-acre campus about a mile north of Luke Air Force Base, with data centers, its own gas-fired power plant and an APS substation. It won a county military compatibility permit and Glendale annexation and rezoning in 2026 despite objections from some residents. Also known as: Project Baccara, Project Eagle, Takanock Baccara.
Who is behind it
The record, newest first
ABC15 reported that the Glendale City Council approved annexation and rezoning for the project, after a 4-2 Planning Commission recommendation with 11 stipulations. (ABC15 Arizona, Oct. 28, 2026)
ABC15 reported that the Arizona Attorney General urged a statewide pause on new data center approvals and looked at how such a pause could affect this Glendale project. (ABC15 Arizona, Sept. 1, 2026)
The Maricopa County Board of Supervisors voted 4-1 to grant the project's military compatibility permit. Air quality permits were still pending. (KJZZ, May 6, 2026)
A pre-annexation development agreement between Glendale and Baccara Eagle Land, LLC was on the Glendale council agenda. It sets private water supply and an APS substation, and describes on-site gas turbines. (City of Glendale (City Council agenda packet), April 28, 2026)
AZBEX reported that Takanock had filed a development permit application with Maricopa County and, in late 2025, applied to the ACC for a certificate of environmental compatibility. It targets a first data center online in Q1 2028. (AZBEX, Jan. 16, 2026)
Conflicts and open questions
- Building descriptions conflict: two two-story buildings of about 1 million sq ft each (AZBEX, Jan 2026), two 500,000 sq ft buildings (the Luke AFB letter in the Glendale agreement), multiple buildings of 100,000-500,000 sq ft (KJZZ), and three buildings of about 330,000 sq ft (ABC15, Sept 2026). Square footage is left null.
- Construction timing conflicts: KJZZ (May 2026) said 2027, and ABC15 (Oct 2026) says the city expects construction to start next month.
- The Luke AFB letter quoted in the agreement says the site sees about 170 overflights a day.
- Developer: Takanock (KJZZ, AZBEX). The applicant entity is Baccara Eagle Land, LLC.
- The ACC line-siting/CEC docket number is not yet captured.
- ABC15 (Oct 2026) breaks the 160 acres down as about 108 acres for three data center buildings, about 33 acres for the gas plant and about 12 acres for a future APS substation; AZBEX gave 23.7 acres for the power plant.
- The ABC15 approval story does not give the council vote count.
The full record
- Status note
- The Maricopa County Board of Supervisors issued a military compatibility permit in May 2026. ABC15 reported on Oct 28, 2026 that the Glendale City Council approved annexation and rezoning, and the city expects construction to start the following month. County and federal air permits were still outstanding as of May 2026.
- Power note
- No data center MW stated. KJZZ reports a 700 MW on-site natural gas power plant (generation, not data center load), and ABC15 reports 18 gas turbines. Generation is not entered in mw.
- Evidence
- Primary public records
- Size class
- 50 MW or more (tracker scope)