Data center campus · Bullard Tech Corridor, Goodyear, Maricopa County, Arizona
Vantage Data Centers Phoenix campus (AZ1)
Operating
as of Oct. 18, 2022
Vantage's three-building, 160 MW campus in Goodyear's Bullard Tech Corridor is its West Valley Phoenix hub. Also known as: Vantage AZ1.
Power160MW reported · stated
Floor area1,000,000sq ft
Site50acres
IT load160MW
Who is behind it
ProjectVantage Data Centers Phoenix campus (AZ1)Also: Vantage AZ1
Developer and teamVantage Data Centers
End userNot found in the recordsNot yet named in any record or credited report we have found.
The record, newest first
Vantage started phase two and said the added capacity would come online in spring 2024. It named APS as the utility. (Vantage Data Centers, Oct. 18, 2022; City of Goodyear, Oct. 18, 2022)
Vantage bought about 50 acres in Goodyear and announced plans for a three-building, 160 MW campus. (Vantage Data Centers, Jan. 8, 2019)
Conflicts and open questions
- Coordinates are approximate, at the Bullard Tech Corridor level; no street address was published.
- The 2022 release describes a 'growing' campus starting phase two but does not state in so many words that phase one is operating.
The full record
- Status note
- Vantage's 2019 release planned a first 32 MW building online in early 2020. In Oct. 2022 Vantage began phase two, with added capacity due in spring 2024.
- Power note
- 160 MW of IT capacity at full build-out across three buildings (Vantage, 2022); the first building was planned at 32 MW of critical load (2019).
- Evidence
- Primary public records
- Size class
- 50 MW or more (tracker scope)