Stream Data Centers Douglas County campus
A Stream affiliate's campus at Winston, west of Douglasville, described in an October 2025 state notice as eight buildings of about 2.39 million sq ft on 215.61 acres, and in undated reports as nine buildings of about 1.34 million sq ft on 246 acres. Also known as: SDC ATLA, LLC.
Who is behind it
The record, newest first
Georgia EPD issued a water-quality certification notice for SDC ATLA, which it identifies as a Stream affiliate, covering eight data center buildings of about 2.39 million sq ft and one substation on 215.61 acres, with comments open to Nov. 21, 2025. Separate undated reports from DCD and Connect CRE describe a Stream regional-impact application through SDC ATLA for nine buildings of about 149,300 sq ft each and two substations on 246 acres, and a nine-building, 1.3 million sq ft Stream plan off Polk Road about 4 miles west of Douglasville. (Georgia Environmental Protection Division, Oct. 22, 2025; DatacenterDynamics, undated; Connect CRE, undated)
Conflicts and open questions
- Size and site differ by source: 246 acres, nine buildings, two substations and about 1.34 million sq ft in DCD and Connect CRE, against 215.61 acres, eight buildings, one substation and about 2.39 million sq ft in the state notice. The fields use the dated state record; no source explains the change.
- DCD and Connect CRE print no date, so their filing is not given a date here.
- The 246 acres is tied to this site by DCD. Connect CRE lists a 246-acre West Atlanta site without linking it to its Polk Road location, so Polk Road is reported only as Connect CRE's description and is not confirmed as the site.
- The DRI number is not given: neither report states it and the state's DRI pages refuse automated reading.
- Separate from the Douglas Waldrop project: that one is 165 acres, filed by TC Atlanta Development.
- Coordinates are approximate, from the road intersection in the state notice.
The full record
- Status note
- The latest dated record is a state water-quality notice from October 2025; no county vote or rezoning record was found.
- Power note
- From DCD's undated report of the regional-impact filing, which said 240 MW, possibly 280 MW within 24 months of a signed lease. The state notice gives no MW.
- Evidence
- Primary public records
- Size class
- 50 MW or more (tracker scope)