Data center campus · West of Wolcott, Mid-America Commerce Park, near U.S. 24 and County Road 1100 West and near Interstate 65, White County, Indiana

Blue Ladder Wolcott data center proposal (Mid-America Commerce Park)

Stalled as of Oct. 15, 2026

A judge in October 2026 reversed White County's 2025 rezoning of farmland at Wolcott's Mid-America Commerce Park, where Blue Ladder Development planned a data center. Also known as: MAC Park.

Cite← Indiana data centers
Adams CountyAllen CountyBartholomew CountyBenton CountyBlackford CountyBoone CountyBrown CountyCarroll CountyCass CountyClark CountyClay CountyClinton CountyCrawford CountyDaviess CountyDearborn CountyDecatur CountyDeKalb CountyDelaware CountyDubois CountyElkhart CountyFayette CountyFloyd CountyFountain CountyFranklin CountyFulton CountyGibson CountyGrant CountyGreene CountyHamilton CountyHancock CountyHarrison CountyHendricks CountyHenry CountyHoward CountyHuntington CountyJackson CountyJasper CountyJay CountyJefferson CountyJennings CountyJohnson CountyKnox CountyKosciusko CountyLaGrange CountyLake CountyLaPorte CountyLawrence CountyMadison CountyMarion CountyMarshall CountyMartin CountyMiami CountyMonroe CountyMontgomery CountyMorgan CountyNewton CountyNoble CountyOhio CountyOrange CountyOwen CountyParke CountyPerry CountyPike CountyPorter CountyPosey CountyPulaski CountyPutnam CountyRandolph CountyRipley CountyRush CountyScott CountyShelby CountySpencer CountySt. Joseph CountyStarke CountySteuben CountySullivan CountySwitzerland CountyTippecanoe CountyTipton CountyUnion CountyVanderburgh CountyVermillion CountyVigo CountyWabash CountyWarren CountyWarrick CountyWashington CountyWayne CountyWells CountyWhite CountyWhitley CountyBlue Ladder Wolcott data center proposal (Mid-America Commerce Park) · Stalled
PowerNot statedNot reported in the records found
Site184acres

Who is behind it

ProjectBlue Ladder Wolcott data center proposal (Mid-America Commerce Park)Also: MAC Park
Developer and teamBlue Ladder Development
End userNot found in the recordsNot yet named in any record or credited report we have found.

The record, newest first

  1. White Circuit Court reverses the rezoning in the neighbors' suit, holding that the county ordinance made a site plan mandatory, the Journal & Courier reports. (Lafayette Journal & Courier (via Yahoo News), Oct. 16, 2026)

  2. Blue Ladder Development schedules a community open house in Monticello on the project. (InkFreeNews (Lafayette Journal & Courier), June 26, 2026)

  3. White County's area plan page links a document labeled as a six-month data center moratorium, dated this day. (White County Area Plan, Nov. 1, 2026)

  4. The White County commissioners approve the rezoning 3-0. (Monticello Herald Journal, Aug. 2025)

  5. The White County Area Plan Commission narrowly recommends rezoning about 287 acres at the park for industrial use. (Inside INdiana Business / IBJ, Aug. 13, 2025)

  6. Two neighbors sue the commissioners, the redevelopment commission and the landowners over the rezoning, alleging the applications lacked a notarized owner letter and a site plan, the Journal & Courier reports. (InkFreeNews (Lafayette Journal & Courier), June 26, 2026; Lafayette Journal & Courier (via Yahoo News), Oct. 16, 2026)

Conflicts and open questions

  • Acreage differs: the Journal & Courier says the reversed rezoning covered more than 184 acres, the figure used here, while IBJ reported about 287 acres at the August 2025 plan commission stage and a commissioner's figure of 250-plus.
  • IBJ's account of the plan commission meeting also reports a 6-4 vote to postpone the rezoning for the water study, which is unclear against the favorable recommendation.
  • Blue Ladder was not a party to the suit. The ruling turned on the rezoning filings, not on whether a data center belongs at the site. The missing owner letters are the plaintiffs' allegation; the judge voiced concern about mismatched dates on the documents.
  • MW and end user are not reported. Officials said in 2025 that the rezoning approved no specific project.
  • The reports give August as the month of the suit without a year; 2025 is inferred from the sequence of events.

The full record

Status note
White Circuit Court reversed the 2025 rezoning on Oct. 15, 2026. Stalled is our reading of that ruling. The developer says it expects a successful appeal, and the landowners could restart the rezoning, with a final vote possible in January.
Evidence
News reports; primary records not yet obtained
Size class
50 MW or more (tracker scope)
Map position approximate, from the reported address or area. Updated Oct. 17, 2026.