Data center campus · Bristol, County Roads 14 and 23, Elkhart County, Indiana

Province Group Bristol data center proposal (County Roads 14 and 23)

Approved as of Sept. 19, 2024

Bristol's town council rezoned about 247 acres of farmland in September 2024 for a $1 billion data center that Province Group was developing for an undisclosed technology company.

Cite← Indiana data centers
Adams CountyAllen CountyBartholomew CountyBenton CountyBlackford CountyBoone CountyBrown CountyCarroll CountyCass CountyClark CountyClay CountyClinton CountyCrawford CountyDaviess CountyDearborn CountyDecatur CountyDeKalb CountyDelaware CountyDubois CountyElkhart CountyFayette CountyFloyd CountyFountain CountyFranklin CountyFulton CountyGibson CountyGrant CountyGreene CountyHamilton CountyHancock CountyHarrison CountyHendricks CountyHenry CountyHoward CountyHuntington CountyJackson CountyJasper CountyJay CountyJefferson CountyJennings CountyJohnson CountyKnox CountyKosciusko CountyLaGrange CountyLake CountyLaPorte CountyLawrence CountyMadison CountyMarion CountyMarshall CountyMartin CountyMiami CountyMonroe CountyMontgomery CountyMorgan CountyNewton CountyNoble CountyOhio CountyOrange CountyOwen CountyParke CountyPerry CountyPike CountyPorter CountyPosey CountyPulaski CountyPutnam CountyRandolph CountyRipley CountyRush CountyScott CountyShelby CountySpencer CountySt. Joseph CountyStarke CountySteuben CountySullivan CountySwitzerland CountyTippecanoe CountyTipton CountyUnion CountyVanderburgh CountyVermillion CountyVigo CountyWabash CountyWarren CountyWarrick CountyWashington CountyWayne CountyWells CountyWhite CountyWhitley CountyProvince Group Bristol data center proposal (County Roads 14 and 23) · Approved
PowerNot statedNot reported in the records found
Floor area1,000,000sq ft
Site247acres

Who is behind it

ProjectProvince Group Bristol data center proposal (County Roads 14 and 23)
Developer and teamThe Province Group
End userNot found in the recordsNot yet named in any record or credited report we have found.

The record, newest first

  1. ABC57 reports few public updates on the project since the 2024 vote. (ABC57, May 20, 2026)

  2. The Bristol Town Council passes the rezoning with four votes in favor and one abstention. (WVPE, Sept. 20, 2024)

  3. WVPE reports that the plan commission favored the rezoning and that the council delayed its vote after a Sept. 5 meeting filled with opponents. (WVPE, Sept. 10, 2024)

Conflicts and open questions

  • Acreage is 247 in one WVPE story and 240 in another; ABC57 says nearly 250. MW and end user are not reported.
  • A separate request to rezone nearly 1,000 acres in Bristol (Bristol Innovation Park) was withdrawn in August 2026; town officials said it carried no specific data center project, and no link to this project was established.

The full record

Status note
The town council approved the rezoning in September 2024. ABC57 said in May 2026 that few public updates had followed.
Evidence
News reports; primary records not yet obtained
Size class
50 MW or more (tracker scope)