Data center campus · 701 Congressional Boulevard, Carmel, Hamilton County, Indiana

Expedient Indianapolis data center

Operating as of Nov. 2026

Expedient operates a 53,000-square-foot data center in Carmel that it markets as its Indianapolis site. Also known as: IND1.

Cite← Indiana data centers
Adams CountyAllen CountyBartholomew CountyBenton CountyBlackford CountyBoone CountyBrown CountyCarroll CountyCass CountyClark CountyClay CountyClinton CountyCrawford CountyDaviess CountyDearborn CountyDecatur CountyDeKalb CountyDelaware CountyDubois CountyElkhart CountyFayette CountyFloyd CountyFountain CountyFranklin CountyFulton CountyGibson CountyGrant CountyGreene CountyHamilton CountyHancock CountyHarrison CountyHendricks CountyHenry CountyHoward CountyHuntington CountyJackson CountyJasper CountyJay CountyJefferson CountyJennings CountyJohnson CountyKnox CountyKosciusko CountyLaGrange CountyLake CountyLaPorte CountyLawrence CountyMadison CountyMarion CountyMarshall CountyMartin CountyMiami CountyMonroe CountyMontgomery CountyMorgan CountyNewton CountyNoble CountyOhio CountyOrange CountyOwen CountyParke CountyPerry CountyPike CountyPorter CountyPosey CountyPulaski CountyPutnam CountyRandolph CountyRipley CountyRush CountyScott CountyShelby CountySpencer CountySt. Joseph CountyStarke CountySteuben CountySullivan CountySwitzerland CountyTippecanoe CountyTipton CountyUnion CountyVanderburgh CountyVermillion CountyVigo CountyWabash CountyWarren CountyWarrick CountyWashington CountyWayne CountyWells CountyWhite CountyWhitley CountyExpedient Indianapolis data center · Operating · 4.4 MW
Power4.4MW reported · record
Floor area53,000sq ft
IT load4.4MW

Who is behind it

ProjectExpedient Indianapolis data centerAlso: IND1
Developer and teamExpedient
End userNot found in the recordsNot yet named in any record or credited report we have found.

The record, newest first

  1. Expedient listed the site at 701 Congressional Boulevard with 4.4 MW of critical IT load when its page was checked on Nov. 1, 2026. (Expedient, undated)

  2. Expedient said it had finished a $4.5 million expansion in Carmel that added 3,500 square feet of computer room and brought raised floor to 26,000 square feet. (Expedient, Nov. 29, 2017)

Conflicts and open questions

  • The current address, size and power come from Expedient's undated location page.

The full record

Status note
Listed on Expedient's location page when checked Nov. 1, 2026.
Power note
Critical IT load per Expedient, which also lists 8.0 MW of generator capacity.
Evidence
Primary public records
Size class
Under 50 MW (outside main scope; kept for completeness)
Map position approximate, from the reported address or area. Updated Oct. 17, 2026.