Google Michigan City data center campus (Project Maize)
Google confirmed in April 2026 that it is taking over the $832 million conversion of a long-vacant factory in Michigan City, where the state approved 70 diesel backup generators. Also known as: Project Maize, 402 Royal Road, Lavender Fields Holdings.
Who is behind it
Phoenix Investors (through Phoenix Michigan City Industrial Investors LLC)
The record, newest first
The city's project page, last changed this day, lists building permits, tax abatement papers, water letters and IDEM notices for the 380,000 to 400,000 square foot conversion. (City of Michigan City, Oct. 21, 2026)
The council tables a resolution on spending the project's expected payments, including $2.5 million for police and fire. (WVPE, July 22, 2026)
ABC57 reports that residents and organizers at a recent community meeting raised concerns about site contamination, light, traffic and unreleased site plans while construction continued. (ABC57, April 19, 2026)
Google confirms it is acquiring the Project Maize site from Phoenix Investors and says it will cover all of the site's power costs and related infrastructure. (WNDU, April 16, 2026; Northwest Indiana Business Magazine, April 17, 2026)
IDEM's approval of the 70-generator air permit is announced. (ABC57, March 23, 2026)
IDEM holds a public meeting on an air permit sought by Lavender Fields Holdings LLC for 70 diesel emergency generators at the site. (ABC57, Dec. 9, 2025)
The Michigan City Common Council approves four resolutions tied to Project Maize, including tax abatements, after attempts to table them fail 5-4. (WVPE, Sept. 4, 2025; WNDU, Sept. 4, 2025)
IBJ reports about $42 million in IEDC tax breaks over 35 years for an unnamed company's $832 million project at 402 Royal Road, a site county property records show under a Phoenix Investors company. (Inside INdiana Business / IBJ, July 10, 2025)
Conflicts and open questions
- MW is not disclosed.
- Acreage is reported as 67 acres (IBJ) and about 70 acres (Northwest Indiana Business). Building size is 380,000 to 400,000 square feet on the city's project page.
- Payment totals differ: WVPE's schedule adds to $25 million, while Northwest Indiana Business reports $26.1 million in benefits to the city, including $1 million for the local economic development group and $100,000 for the sanitary district.
- The air permit applicant is spelled both Lavender and Lavendar in records and reporting. ABC57 wrote that it suspected the applicant stood in for a large technology company; no opened record ties it to Google.
- The city's project page says the site is near a NIPSCO substation and plans a customer-owned substation, but no opened record names the serving utility.
- File names on the city page show an IDEM public comment notice received Oct. 12, 2026 and an extension received Oct. 20, 2026; their contents were not read.
The full record
- Status note
- Reported under construction in April 2026, and a council member described nearly a year of construction effects in July 2026. No completion date is public.
- Evidence
- Primary public records
- Size class
- Under 50 MW (outside main scope; kept for completeness)