Data center campus · Greensburg, north of town in the Business Enterprise Park along I-74, opposite Honda's plant, Decatur County, Indiana

Jumping Bison Greensburg data center proposal

Proposed as of Jan. 13, 2026

Greensburg approved a partial tax abatement in December 2024 for Jumping Bison's planned two-phase, $800 million data center, which had not broken ground as of January 2026.

Cite← Indiana data centers
Adams CountyAllen CountyBartholomew CountyBenton CountyBlackford CountyBoone CountyBrown CountyCarroll CountyCass CountyClark CountyClay CountyClinton CountyCrawford CountyDaviess CountyDearborn CountyDecatur CountyDeKalb CountyDelaware CountyDubois CountyElkhart CountyFayette CountyFloyd CountyFountain CountyFranklin CountyFulton CountyGibson CountyGrant CountyGreene CountyHamilton CountyHancock CountyHarrison CountyHendricks CountyHenry CountyHoward CountyHuntington CountyJackson CountyJasper CountyJay CountyJefferson CountyJennings CountyJohnson CountyKnox CountyKosciusko CountyLaGrange CountyLake CountyLaPorte CountyLawrence CountyMadison CountyMarion CountyMarshall CountyMartin CountyMiami CountyMonroe CountyMontgomery CountyMorgan CountyNewton CountyNoble CountyOhio CountyOrange CountyOwen CountyParke CountyPerry CountyPike CountyPorter CountyPosey CountyPulaski CountyPutnam CountyRandolph CountyRipley CountyRush CountyScott CountyShelby CountySpencer CountySt. Joseph CountyStarke CountySteuben CountySullivan CountySwitzerland CountyTippecanoe CountyTipton CountyUnion CountyVanderburgh CountyVermillion CountyVigo CountyWabash CountyWarren CountyWarrick CountyWashington CountyWayne CountyWells CountyWhite CountyWhitley CountyJumping Bison Greensburg data center proposal · Proposed
PowerNot statedNot reported in the records found
Site340acres

Who is behind it

ProjectJumping Bison Greensburg data center proposal
Developer and teamJumping Bison LLC
End userNot found in the recordsNot yet named in any record or credited report we have found.

The record, newest first

  1. Decatur County commissioners adopt Ordinance 2026-15, a data center moratorium running through the end of December 2026. (Greensburg Daily News, Sept. 22, 2026)

  2. About 40 to 50 people fill a standing-room council meeting, many to oppose the project, though it is not on the agenda; the council president reads aloud an email he sent fellow councilors about it. (WTRE, Jan. 13, 2026; Greensburg Daily News, Jan. 15, 2026; WRBI Radio, via Ground News, Jan. 15, 2026)

  3. DCD reports that a petition opposing the project has more than 950 signatures. (DatacenterDynamics, Oct. 29, 2025)

  4. The Greensburg City Council approves a 10-year, 60% real property tax abatement for the project. (WTRE Radio, Dec. 10, 2024; Greensburg Daily News (via AOL), Dec. 11, 2024)

Conflicts and open questions

  • Acreage is disputed: Greensburg Daily News reports about 340 acres and DCD reports 550 acres.
  • Greensburg Daily News says the city annexed the 340 acres in 2024. The moratorium story as read does not mention this project, and whether the moratorium reaches annexed city land was not confirmed.
  • The operator behind Jumping Bison LLC and the MW are not reported. No record about the project after January 2026 was found.

The full record

Status note
As of mid-January 2026 Greensburg Daily News reported no groundbreaking, and WTRE reported no related item before any city board or commission.
Evidence
News reports; primary records not yet obtained
Size class
50 MW or more (tracker scope)
Map position approximate, from the reported address or area. Updated Oct. 17, 2026.