Data center campus · La Porte, Thomas Rose Industrial Park (northeast side of the city), LaPorte County, Indiana

La Porte One data center proposal (Thomas Rose Industrial Park)

Proposed as of Jan. 13, 2026

A special-purpose company won a height variance in January 2026 for five data center buildings on about 110 acres in La Porte's Thomas Rose Industrial Park. Also known as: LaPorte 1, LLC.

Cite← Indiana data centers
Adams CountyAllen CountyBartholomew CountyBenton CountyBlackford CountyBoone CountyBrown CountyCarroll CountyCass CountyClark CountyClay CountyClinton CountyCrawford CountyDaviess CountyDearborn CountyDecatur CountyDeKalb CountyDelaware CountyDubois CountyElkhart CountyFayette CountyFloyd CountyFountain CountyFranklin CountyFulton CountyGibson CountyGrant CountyGreene CountyHamilton CountyHancock CountyHarrison CountyHendricks CountyHenry CountyHoward CountyHuntington CountyJackson CountyJasper CountyJay CountyJefferson CountyJennings CountyJohnson CountyKnox CountyKosciusko CountyLaGrange CountyLake CountyLaPorte CountyLawrence CountyMadison CountyMarion CountyMarshall CountyMartin CountyMiami CountyMonroe CountyMontgomery CountyMorgan CountyNewton CountyNoble CountyOhio CountyOrange CountyOwen CountyParke CountyPerry CountyPike CountyPorter CountyPosey CountyPulaski CountyPutnam CountyRandolph CountyRipley CountyRush CountyScott CountyShelby CountySpencer CountySt. Joseph CountyStarke CountySteuben CountySullivan CountySwitzerland CountyTippecanoe CountyTipton CountyUnion CountyVanderburgh CountyVermillion CountyVigo CountyWabash CountyWarren CountyWarrick CountyWashington CountyWayne CountyWells CountyWhite CountyWhitley CountyLa Porte One data center proposal (Thomas Rose Industrial Park) · Proposed
PowerNot statedNot reported in the records found
Site110acres

Who is behind it

ProjectLa Porte One data center proposal (Thomas Rose Industrial Park)Also: LaPorte 1, LLC
Developer and teamLa Porte One LLC
End userNot found in the recordsNot yet named in any record or credited report we have found.

The record, newest first

  1. A county commissioner tells a public meeting that the Thomas Rose proposal exists but that nothing has been filed with county plan or building offices. (ABC57, Feb. 21, 2026)

  2. The La Porte Board of Zoning Appeals unanimously allows five air-cooled data center buildings to reach 65 feet. (Hometown News Now, Jan. 19, 2026; La Porte Herald-Dispatch, Jan. 2026; ABC57, Jan. 16, 2026)

Conflicts and open questions

  • The company's name appears as both La Porte One LLC and LaPorte 1, LLC. Hometown News Now says two unnamed developers formed it.
  • MW and end user are not reported. No record after February 2026 was found.

The full record

Status note
The La Porte Board of Zoning Appeals approved a height variance on Jan. 13, 2026. A final site plan still needs city approval, and a local economic development official said the developers were still asking whether the project was possible.
Evidence
News reports; primary records not yet obtained
Size class
50 MW or more (tracker scope)
Map position approximate, from the reported address or area. Updated Oct. 17, 2026.