Data center campus · Northwest of Frankfort near I-65, in the area north of the Frito Lay plant and northeast of the Conagra facility, Clinton County, Indiana

Logistix Realty Frankfort data center campus (Clinton County)

Denied as of Jan. 20, 2026

A developer's plan for a 300 MW campus of more than $10 billion beside I-65 at Frankfort was pulled from the city process in 2025 and denied by Clinton County commissioners in January 2026. Also known as: Logix Realty LLC petition, Data One rezoning.

Cite← Indiana data centers
Adams CountyAllen CountyBartholomew CountyBenton CountyBlackford CountyBoone CountyBrown CountyCarroll CountyCass CountyClark CountyClay CountyClinton CountyCrawford CountyDaviess CountyDearborn CountyDecatur CountyDeKalb CountyDelaware CountyDubois CountyElkhart CountyFayette CountyFloyd CountyFountain CountyFranklin CountyFulton CountyGibson CountyGrant CountyGreene CountyHamilton CountyHancock CountyHarrison CountyHendricks CountyHenry CountyHoward CountyHuntington CountyJackson CountyJasper CountyJay CountyJefferson CountyJennings CountyJohnson CountyKnox CountyKosciusko CountyLaGrange CountyLake CountyLaPorte CountyLawrence CountyMadison CountyMarion CountyMarshall CountyMartin CountyMiami CountyMonroe CountyMontgomery CountyMorgan CountyNewton CountyNoble CountyOhio CountyOrange CountyOwen CountyParke CountyPerry CountyPike CountyPorter CountyPosey CountyPulaski CountyPutnam CountyRandolph CountyRipley CountyRush CountyScott CountyShelby CountySpencer CountySt. Joseph CountyStarke CountySteuben CountySullivan CountySwitzerland CountyTippecanoe CountyTipton CountyUnion CountyVanderburgh CountyVermillion CountyVigo CountyWabash CountyWarren CountyWarrick CountyWashington CountyWayne CountyWells CountyWhite CountyWhitley CountyLogistix Realty Frankfort data center campus (Clinton County) · Denied · 300 MW
Power300MW reported · stated
Floor area7,000,000sq ft
Site715acres

Who is behind it

ProjectLogistix Realty Frankfort data center campus (Clinton County)Also: Logix Realty LLC petition, Data One rezoning
Developer and teamLogistix Realty (through Logix Realty LLC)
End userNot found in the recordsNot yet named in any record or credited report we have found.

The record, newest first

  1. County commissioners deny the rezoning of about 715 acres from agricultural to light industrial by a 3-0 vote. (Clinton County Today, Jan. 20, 2026; Frankfort Times, Jan. 2026)

  2. The Clinton County Area Plan Commission gives the rezoning a favorable recommendation. (Clinton County Today, Jan. 20, 2026)

  3. IBJ reports the plan: 718 acres, about 7 million square feet, up to 350 permanent jobs and no signed end user. (Inside INdiana Business / IBJ, July 17, 2025)

  4. The developer withdraws its request to the city for rezoning before a July 23 plan commission hearing and says it will go to county authorities instead. (Data Center Dynamics, July 2025)

  5. The Frankfort Utility Service Board approves a non-binding letter offering up to 300 MW, valid for three years and conditional on the customer paying all costs. (Clinton County Today, July 19, 2025)

Conflicts and open questions

  • Acreage differs by source and stage: 714.55 acres (Clinton County Today), about 715 (Frankfort Times), 718 (IBJ, July 2025), 833 (Data Center Dynamics).
  • Clinton County Today names the petitioner as Logix Reality LLC, Data Center Dynamics as Logix Realty LLC, a Logistix affiliate, and the Frankfort Times names the developer as Data One. How Data One relates to Logistix was not established. The link from the January 2026 denial to Logistix rests on the Logix petitioner name and the acreage.
  • Data Center Dynamics' piece and the Frankfort Times piece show no date on the copies opened, so their dates are approximate.

The full record

Status note
County commissioners denied the rezoning 3-0 on Jan. 20, 2026, and Clinton County Today and the Frankfort Times report a 12-month wait before the same or a substantially similar request can return.
Power note
Up to 300 MW is the capacity in a non-binding will-serve letter approved by the Frankfort utility board and the figure the developer gave IBJ.
Evidence
News reports; primary records not yet obtained
Size class
50 MW or more (tracker scope)
Map position approximate, from the reported address or area. Updated Oct. 17, 2026.