New Carlisle 25 data center proposal (Chicago Trail, Olive Township)
A separate proposal from Amazon's campus, this 14-building plan on about 1,057 acres of farmland north of New Carlisle lost its rezoning vote at the county council in December 2025.
Who is behind it
The record, newest first
The county council rejects the rezoning 7-2. (WVPE, Dec. 10, 2025; WNDU, Dec. 9, 2025; ABC57, Dec. 10, 2025; ABC57, Dec. 9, 2025)
WNDU reports that the New Carlisle Town Council filed a resolution opposing the rezoning. (WNDU, Oct. 23, 2025)
The council's land use committee gives the rezoning an unfavorable recommendation on a 3-2 vote. (WNDU, Dec. 9, 2025)
The county council postpones its rezoning decision so the developers can talk further with the community, DCD reports. (DatacenterDynamics, 2025)
The St. Joseph County Area Plan Commission votes 7-0 to send the rezoning to the council with an unfavorable recommendation. (WVPE, Sept. 17, 2025; ABC57, Sept. 18, 2025)
The county council sends an ordinance rezoning more than 1,000 acres from agricultural to industrial to its land use committee. (Inside INdiana Business, May 14, 2025)
Conflicts and open questions
- This is not part of aws-new-carlisle-project-rainier. Reporting describes it as a further data center on farmland outside the Indiana Enterprise Center.
- Investment is $12 billion in WNDU and DCD and $13 billion in ABC57. Acreage is 1,057 in ABC57 and DCD and about 1,000 in WVPE.
- ABC57 called Mall-o-Manor LLC the developer, while DCD, citing the South Bend Tribune, lists it among the landowners and names New Carlisle 25 Developer LLC as the buyer.
- The council president wrote that Meta would be the end user and later revised that to speculation; Meta told WSBT the site was not its own (DCD).
- MW and end user are not reported. No 2026 refiling was found.
The full record
- Status note
- The St. Joseph County Council voted 7-2 against the rezoning after a meeting that ran into the early morning. ABC57 reported that the petition can be brought back.
- Evidence
- News reports; primary records not yet obtained
- Size class
- 50 MW or more (tracker scope)