Data center campus · 1800 Cristiani Parkway, Shadow Lake Business Park, Charlestown, Clark County, Indiana

QLEVR Charlestown data center (Shadow Lake Business Park)

Approved as of July 20, 2026

A small $105 million data center won a 4-3 plan commission vote despite a resident petition, and Charlestown then paused any further data center proposals for a year.

Cite← Indiana data centers
Adams CountyAllen CountyBartholomew CountyBenton CountyBlackford CountyBoone CountyBrown CountyCarroll CountyCass CountyClark CountyClay CountyClinton CountyCrawford CountyDaviess CountyDearborn CountyDecatur CountyDeKalb CountyDelaware CountyDubois CountyElkhart CountyFayette CountyFloyd CountyFountain CountyFranklin CountyFulton CountyGibson CountyGrant CountyGreene CountyHamilton CountyHancock CountyHarrison CountyHendricks CountyHenry CountyHoward CountyHuntington CountyJackson CountyJasper CountyJay CountyJefferson CountyJennings CountyJohnson CountyKnox CountyKosciusko CountyLaGrange CountyLake CountyLaPorte CountyLawrence CountyMadison CountyMarion CountyMarshall CountyMartin CountyMiami CountyMonroe CountyMontgomery CountyMorgan CountyNewton CountyNoble CountyOhio CountyOrange CountyOwen CountyParke CountyPerry CountyPike CountyPorter CountyPosey CountyPulaski CountyPutnam CountyRandolph CountyRipley CountyRush CountyScott CountyShelby CountySpencer CountySt. Joseph CountyStarke CountySteuben CountySullivan CountySwitzerland CountyTippecanoe CountyTipton CountyUnion CountyVanderburgh CountyVermillion CountyVigo CountyWabash CountyWarren CountyWarrick CountyWashington CountyWayne CountyWells CountyWhite CountyWhitley CountyQLEVR Charlestown data center (Shadow Lake Business Park) · Approved · 5 MW
Power5MW reported · stated
Floor area55,000sq ft
Site12acres

Who is behind it

ProjectQLEVR Charlestown data center (Shadow Lake Business Park)
Developer and teamQLEVR
ION Louis LLC
End userNot found in the recordsNot yet named in any record or credited report we have found.

The record, newest first

  1. The common council votes 5-0 for a one-year moratorium on further data centers and battery storage that does not stop this project. (News and Tribune, Aug. 5, 2026)

  2. The advisory plan commission votes 4-3 that the plan meets zoning, with stipulations. (Louisville Public Media, July 21, 2026; News and Tribune, Aug. 5, 2026)

  3. Data Center Dynamics reports the plan is due before the plan commission, with residents raising noise, traffic and environmental concerns. (Data Center Dynamics, June 8, 2026)

Conflicts and open questions

  • Petition count differs: more than 800 signatures in Louisville Public Media, about 500 in the News and Tribune.
  • Louisville Public Media spells the developer Qlever LLC, based in Tampa; Data Center Dynamics uses QLevr; the News and Tribune uses QLEVR.
  • Sq. ft.: about 55,000; Data Center Dynamics gives 55,000 to 60,000.

The full record

Status note
The advisory plan commission found the development plan met light industrial zoning, with conditions for a berm, blasting surveys and an environmental study.
Power note
Under 50 MW. Sources differ: 3 MW in Data Center Dynamics; up to 5 MW at full build-out in Louisville Public Media.
Evidence
News reports; primary records not yet obtained
Size class
Under 50 MW (outside main scope; kept for completeness)