Data center campus · Elkhart County; the utility testimony gives only the county and a parcel crossed by the Hiple-East Elkhart 345 kV line., Elkhart County, Indiana

Takanock Elkhart County data center proposal (Takanock Beckham)

Stalled as of April 1, 2025

Takanock told Indiana utility regulators in 2025 that it wanted NIPSCO service for about 1.5 GW at an Elkhart County site but was at an impasse with the utility over interconnection. Also known as: Project Beckham.

Cite← Indiana data centers
Adams CountyAllen CountyBartholomew CountyBenton CountyBlackford CountyBoone CountyBrown CountyCarroll CountyCass CountyClark CountyClay CountyClinton CountyCrawford CountyDaviess CountyDearborn CountyDecatur CountyDeKalb CountyDelaware CountyDubois CountyElkhart CountyFayette CountyFloyd CountyFountain CountyFranklin CountyFulton CountyGibson CountyGrant CountyGreene CountyHamilton CountyHancock CountyHarrison CountyHendricks CountyHenry CountyHoward CountyHuntington CountyJackson CountyJasper CountyJay CountyJefferson CountyJennings CountyJohnson CountyKnox CountyKosciusko CountyLaGrange CountyLake CountyLaPorte CountyLawrence CountyMadison CountyMarion CountyMarshall CountyMartin CountyMiami CountyMonroe CountyMontgomery CountyMorgan CountyNewton CountyNoble CountyOhio CountyOrange CountyOwen CountyParke CountyPerry CountyPike CountyPorter CountyPosey CountyPulaski CountyPutnam CountyRandolph CountyRipley CountyRush CountyScott CountyShelby CountySpencer CountySt. Joseph CountyStarke CountySteuben CountySullivan CountySwitzerland CountyTippecanoe CountyTipton CountyUnion CountyVanderburgh CountyVermillion CountyVigo CountyWabash CountyWarren CountyWarrick CountyWashington CountyWayne CountyWells CountyWhite CountyWhitley CountyTakanock Elkhart County data center proposal (Takanock Beckham) · Stalled · 1,500 MW
Power1,500MW reported · record

Who is behind it

ProjectTakanock Elkhart County data center proposal (Takanock Beckham)Also: Project Beckham
Developer and teamTakanock (through Takanock Beckham, LLC)
End userNot found in the recordsNot yet named in any record or credited report we have found.

The record, newest first

  1. Takanock files testimony in IURC Cause No. 46183 describing its roughly 1.5 GW project and the dispute over connecting it. (Indiana Utility Regulatory Commission, April 1, 2025)

  2. According to Takanock's testimony, NIPSCO offers to study only one option: two new 345 kV lines running more than 15 miles. (Indiana Utility Regulatory Commission, April 1, 2025)

  3. According to Takanock's testimony, NIPSCO calls its application incomplete and separately says no end user is identified on it. (Indiana Utility Regulatory Commission, April 1, 2025)

  4. Takanock testifies that it first approached NIPSCO about serving the site in this month. (Indiana Utility Regulatory Commission, April 1, 2025)

Conflicts and open questions

  • This account is Takanock's side of a contested docket; NIPSCO's response was not reviewed. The case itself is a NIPSCO Generation petition on commission jurisdiction, in which Takanock intervened.
  • Coordinates are county-level only. The testimony names no town.
  • Whether Takanock has dropped the project is unconfirmed.

The full record

Status note
In April 2025 testimony at the IURC, Takanock described an impasse with NIPSCO over how to connect the site. Stalled is our reading of that testimony; no later record of the project's status was opened.
Power note
Takanock's testimony describes NIPSCO's response as sized for an estimated 1.5 GW of data center load; its own modeling shows about 1,350 MW available on the line.
Evidence
Primary public records
Size class
50 MW or more (tracker scope)
Map position approximate, from the reported address or area. Updated Oct. 17, 2026.