Data center campus · 7151 and 7350 Century Park Drive and 8401 and 8501 Vulcan Lane, Manassas area, Prince William, Virginia

Amazon land at Century Park Drive and Vulcan Lane, Manassas

Site zoned or marketed as of Jan. 2024

Amazon's data center arm paid about $152 million for some 140 acres in two clusters near Manassas that are already zoned for data centers.

Cite← Virginia data centers
AccomackAlbemarleAlexandriaAlleghanyAmeliaAmherstAppomattoxArlingtonAugustaBathBedfordBlandBotetourtBristolBrunswickBuchananBuckinghamBuena VistaCampbellCarolineCarrollCharles CityCharlotteCharlottesvilleChesapeakeChesterfieldClarkeColonial HeightsCovingtonCraigCulpeperCumberlandDanvilleDickensonDinwiddieEmporiaEssexFairfaxFairfax (city)Falls ChurchFauquierFloydFluvannaFranklinFranklin (city)FrederickFredericksburgGalaxGilesGloucesterGoochlandGraysonGreeneGreensvilleHalifaxHamptonHanoverHarrisonburgHenricoHenryHighlandHopewellIsle of WightJames CityKing and QueenKing GeorgeKing WilliamLancasterLeeLexingtonLoudounLouisaLunenburgLynchburgMadisonManassasManassas ParkMartinsvilleMathewsMecklenburgMiddlesexMontgomeryNelsonNew KentNewport NewsNorfolkNorthamptonNorthumberlandNortonNottowayOrangePagePatrickPetersburgPittsylvaniaPoquosonPortsmouthPowhatanPrince EdwardPrince GeorgePrince WilliamPulaskiRadfordRappahannockRichmondRichmond (city)RoanokeRoanoke (city)RockbridgeRockinghamRussellSalemScottShenandoahSmythSouthamptonSpotsylvaniaStaffordStauntonSuffolkSurrySussexTazewellVirginia BeachWarrenWashingtonWaynesboroWestmorelandWilliamsburgWinchesterWiseWytheYorkAmazon land at Century Park Drive and Vulcan Lane, Manassas · Site zoned or marketed
PowerNot statedNot reported in the records found
Site140acres

Who is behind it

ProjectAmazon land at Century Park Drive and Vulcan Lane, Manassas
Developer and teamAmazon Data Services
End userAmazon Web Services

The record, newest first

  1. Connect CRE, citing the Washington Business Journal, reported Amazon Data Services bought about 27 acres on Century Park Drive and 113 acres on Vulcan Lane, next to a Vulcan Materials quarry, for about $152 million. (Connect CRE, Jan. 24, 2024)

Conflicts and open questions

  • The two parcel clusters are grouped as one entry because they were bought together; split them if later records show separate campuses.
  • Coordinates approximate, placed near Century Park Drive from the reported addresses.
  • The lead's '7101 Century Park Drive' address was not found in any record opened.
  • Amazon holds DEQ air permits for many Prince William buildings, but the public list gives no addresses, so none could be tied to this land.

The full record

Status note
Amazon Data Services bought the land, which sits in the county's Data Center Opportunity Zone Overlay District; no site plan or construction record was opened.
Power note
No power figure reported.
Evidence
News reports; primary records not yet obtained
Size class
50 MW or more (tracker scope)
Map position approximate, from the reported address or area. Updated Oct. 17, 2026.