Data center campus · 8535 and 8451 Highfield Parkway, Englewood, Douglas County, Colorado
EdgeConneX Denver campus
Operating
as of March 23, 2026
A two-building colocation site in the Highfield business park, with one building operating and a second building's data halls still planned. Also known as: DEN01, DEN02.
Power3MW reported · stated
Floor area145,300sq ft
Who is behind it
ProjectEdgeConneX Denver campusAlso: DEN01, DEN02
Developer and teamEdgeConneX
End userNot found in the recordsNot yet named in any record or credited report we have found.
The record, newest first
EdgeConneX's location page, last modified on this date, lists DEN01 at 29,800 sq ft and 3 MW with 1.5 MW under way, and DEN02 at 115,500 sq ft with five planned data halls. (EdgeConneX, March 23, 2026; EdgeConneX, undated; datacenterHawk, undated)
Conflicts and open questions
- DEN02 capacity differs within EdgeConneX's own material: up to 24 MW (web page) and up to 19.2 MW (data sheet).
- Square footage is the sum of both buildings; datacenterHawk's listing says DEN02 has not yet been commissioned or leased.
- County: the Census geocoder places both addresses in Douglas County, close to the Arapahoe line, despite the Englewood mailing address.
The full record
- Status note
- DEN01 is in service with an expansion in progress; DEN02's five data halls are listed as planned.
- Power note
- Current N+1 capacity at DEN01 per EdgeConneX, with 1.5 MW more being built. DEN02 is listed at up to 24 MW on the company's web page and up to 19.2 MW on its data sheet, which gives a campus total of 21 potential MW.
- Evidence
- Primary public records
- Size class
- Under 50 MW (outside main scope; kept for completeness)