Data center campus · Miami-Dade County, within 10 to 14 miles of downtown Miami (operator gives no street address), Miami-Dade County, Florida

EdgeConneX MIA01

Operating as of March 23, 2026

EdgeConneX's smaller Miami-area data center, a 27,000-square-foot building with 1.5 MW, about 10 miles from Miami International Airport.

Cite← Florida data centers
Alachua CountyBaker CountyBay CountyBradford CountyBrevard CountyBroward CountyCalhoun CountyCharlotte CountyCitrus CountyClay CountyCollier CountyColumbia CountyDeSoto CountyDixie CountyDuval CountyEscambia CountyFlagler CountyFranklin CountyGadsden CountyGilchrist CountyGlades CountyGulf CountyHamilton CountyHardee CountyHendry CountyHernando CountyHighlands CountyHillsborough CountyHolmes CountyIndian River CountyJackson CountyJefferson CountyLafayette CountyLake CountyLee CountyLeon CountyLevy CountyLiberty CountyMadison CountyManatee CountyMarion CountyMartin CountyMiami-Dade CountyMonroe CountyNassau CountyOkaloosa CountyOkeechobee CountyOrange CountyOsceola CountyPalm Beach CountyPasco CountyPinellas CountyPolk CountyPutnam CountySanta Rosa CountySarasota CountySeminole CountySt. Johns CountySt. Lucie CountySumter CountySuwannee CountyTaylor CountyUnion CountyVolusia CountyWakulla CountyWalton CountyWashington CountyEdgeConneX MIA01 · Operating · 1.5 MW
Power1.5MW reported · stated
Floor area27,000sq ft

Who is behind it

ProjectEdgeConneX MIA01
Developer and teamEdgeConneX
End userNot found in the recordsNot yet named in any record or credited report we have found.

The record, newest first

  1. EdgeConneX's Miami page lists MIA01 at 27,000 square feet with 11,300 square feet of raised floor. (EdgeConneX, March 23, 2026)

  2. The Q1 2026 data sheet gives MIA01 1.5 MW at N+1. (EdgeConneX, March 1, 2026)

Conflicts and open questions

  • EdgeConneX's web page and data sheet disagree on MIA01's distance from downtown (14 vs. 10 miles); neither gives an address.
  • The data sheet date is approximate, from its upload path.
  • No street address confirmed from an opened, citable source; coordinates are set to central Miami as the nearest city and should be refined.

The full record

Status note
EdgeConneX's Miami page (last modified March 23, 2026) lists MIA01 as one of its two Miami data centers.
Power note
Under 50 MW. EdgeConneX's data sheet lists 1.5 MW at N+1 for MIA01.
Evidence
Primary public records
Size class
Under 50 MW (outside main scope; kept for completeness)
Map position approximate, from the reported address or area. Updated Nov. 7, 2026.