Data center campus · Along Westland and Cottonwood Bend roads, west of Hermiston, near the Hermiston Generating Plant, Umatilla County, Oregon

Amazon (AWS) campus, Westland and Cottonwood Bend roads, Umatilla County

Operating as of July 12, 2023

An Amazon campus on 120 acres rezoned from farm use by Umatilla County in 2017, planned for four buildings and listed with three in 2023. Also known as: Westland.

Cite← Oregon data centers
Baker CountyBenton CountyClackamas CountyClatsop CountyColumbia CountyCoos CountyCrook CountyCurry CountyDeschutes CountyDouglas CountyGilliam CountyGrant CountyHarney CountyHood River CountyJackson CountyJefferson CountyJosephine CountyKlamath CountyLake CountyLane CountyLincoln CountyLinn CountyMalheur CountyMarion CountyMorrow CountyMultnomah CountyPolk CountySherman CountyTillamook CountyUmatilla CountyUnion CountyWallowa CountyWasco CountyWashington CountyWheeler CountyYamhill CountyAmazon (AWS) campus, Westland and Cottonwood Bend roads, Umatilla County · Operating
PowerNot statedNot reported in the records found
Site120acres

Who is behind it

ProjectAmazon (AWS) campus, Westland and Cottonwood Bend roads, Umatilla CountyAlso: Westland
End userNot found in the recordsNot yet named in any record or credited report we have found.

The record, newest first

  1. A Hermiston planning staff report, comparing parking at other Amazon sites, listed Westland at about 100 spaces for three buildings. (City of Hermiston Planning Commission, July 12, 2023)

  2. All three county commissioners approved the zone change after a hearing where no one testified against it; 1000 Friends of Oregon had sent a letter questioning industrial use of the land. (East Oregonian, April 14, 2017)

  3. The county planning commission heard Vadata's request to move about 120 acres from Exclusive Farm Use to Light Industrial with a limited use overlay and voted 7-1 to recommend it; the vice chair, the one no vote, objected to losing farmland. (Northeast Oregon Now, undated; Hermiston Herald, March 29, 2017; The Spokesman-Review (Associated Press), March 20, 2017)

  4. Trade press reported Vadata had signed a letter of intent to use the regional water system and had agreed to pay for needed improvements. (Data Center Knowledge, March 21, 2017)

Conflicts and open questions

  • The Hermiston report says Westland but gives no address; it is matched to the 2017 rezoning site by the shared Westland name and location.
  • The map point is approximate, from the reported location southwest of Hermiston near the Hermiston Generating Plant.

The full record

Status note
A 2023 City of Hermiston staff report lists Amazon's Westland facility with three buildings; the 2017 plan was for four.
Power note
No power figure in the records reviewed.
Evidence
Primary public records
Size class
50 MW or more (tracker scope)